Case Study 10
Client: Mr & Mrs Docherty
Location: Gourock
Value: £14000
Completed: November 2014
The project commenced on October 2014 and was for the design and installation of a new driveway, walling and steps. The client had a driveway installed by cold callers a few months prior to us commencing. The installation was of unacceptable quality.
KEY ISSUES
- Situated close to the local primary school, consideration had to be taken for school children and traffic, making sure that deliveries where within school hours.
- 40 tons of excavations
- Lighting
- Drainage
- Retaining wall
Principal Elements included:
100m2 of Marshalls Elise block paving.
20m2 of walling
40 tons of type 1 sub-base